Two NEEPCO projects in Arunachal to be commissioned next year

Two NEEPCO projects in Arunachal to be commissioned next year

The North Eastern Electric Power Corporation (NEEPCO) has said that its two hydro electric projects in Arunachal Pradesh are on the verge of completion and they would be commissioned next year.

Commissioning of the 600 MW Kameng Hydro Electric Project and the 110 MW Pare Hydro Electric Project was delayed by about a couple of months due to floods and landslides.

“The Pare Hydro Project is set to be commissioned by February end next year, while the Kameng project would take another two months,” NEEPCO Personnel Director S Borgohain said.

Besides the Pare and Kameng electric projects, NEEPCO runs the 405 MW Ranganadi hydro electric project in Lower Subansiri district, which was commissioned in 2002.